Aging Energy Infrastructure

Guestwords in the East Hampton Star

By David Posnett March 17, 2021

On the South Fork of Long Island, we all know about yearly brownouts during peak demand for power in the summer. Indeed, energy demand on the South Fork is growing at almost twice the rate of the rest of Long Island.

And now we have witnessed the power outages in Texas during freezing weather. With decades of neglect of their power grids, refusal to update the necessary infrastructure, and an ill-advised policy of not building connections with out-of-state grids, many lives were lost and the economic fallout is still unknown.

Locally, two major blackouts in 1965 and 1977 paralyzed New York City and exposed the vulnerability of the power grid. The full story can be read by Googling “Gaslights to Generators,” a September 2002 article on New York City’s energy history by Meryl Feiner.

Long Island is in a precarious situation in terms of meeting growing energy demands. Historically the Island has not produced sufficient energy, and thus it imports energy from elsewhere. But with solar and now wind energy sources, this is about to change. There are plans for 4,000 megawatts from wind farms off Long Island shores and 130 megawatts from the South Fork Wind farm, the project that is furthest along.

An interesting article in Newsday by Mark Harrington, updated on Feb. 24, discusses a NYSERDA (New York State Energy Research and Development Authority) report on the required updates to the grid and the infrastructure required to manage the massive new clean energy sources being planned. Harrington quotes Tom Falcone, chief executive of the Long Island Power Authority, saying, “As you put more and more offshore wind onto the grid, think of it as water pipe. At some point you reach the limit, so in order to have more offshore wind you have to upgrade the pipe.”

If we do nothing, the report indicates, there would be a need for “curtailments,” or intentional power outages.

The total cost of the required infrastructure updates would be about $1.5 billion. The upgrades include building a 345,000-volt circuit from LIPA’s newly built Shore Road substation in Glenwood Landing to the substation in Melville, an upgrade of the South Shore transmission grid (already in process), conversion of an existing 138,000-volt transmission line in Levittown to 345,000 volts, a new interconnection line between the LIPA and Con Edison systems, solar power upgrades of various substations, and improvements that are either already part of LIPA’s capital budget or have already begun, such as upgrading transformers and switching gear and substations to higher voltages.

A full list of LIPA’s transmission system and distribution system projects was presented on Feb. 24 at the LIPA trustee meeting. The slide deck can be found at lipower.org.

I asked some experts the following question: Would these grid upgrades also be required if the source of the required extra energy were solely fossil fuel generated, and to what extent are the costs a result of converting to clean energy?

“It is clear that we need to increase the capacity and resilience of the Long Island grid, so let’s get to work on the immediate upgrades and retrofits necessary within the current infrastructure,” said Mariah Dignan of Climate Jobs NY and the Climate Jobs NY Education Fund. “But as we begin to realize the clean energy economy, we will need bulk power transmission and distribution voltage upgrades over the next decade to handle offshore wind generation, increased electrification, and a better flow of renewables from upstate to downstate and vice versa. These investments will pay off for decades to come, and labor is fighting to ensure this transformation creates good union jobs and protects Long Island ratepayers.”

Gordian Raacke, the executive director of Renewable Energy Long Island, said that if the same amount of capacity would be interconnected at the same locations, similar grid upgrades and costs would be needed for fossil fuel versus renewable energy. But it is also fair to say that fossil fuel generation could be located in other parts of the state, while offshore wind resources would have to be interconnected along the shore.

In addition, he said, there are several misunderstandings that need to be cleared up. First, the potential transmission and distribution upgrades are not associated with the South Fork Wind farm but with all of the offshore wind farms that would be connected to the Long Island grid, as well as the interconnection of distributed solar and energy storage projects. These costs would not be borne exclusively by Long Island ratepayers but shared across New York State. These are potential projects identified in studies and proposed for study. LIPA does not believe that all of these “possible transmission projects” will be built. And last, most of the transmission projects would not be needed until 2025 through 2035.

Gordian has often reminded us, from the beginning, that the energy infrastructure must be renewed or replaced regardless of wind farms. This is a really costly undertaking, and it’s terrific that PSEG is proposing to make it a state­wide charge to ratepayers.

Get with the Program

LTE published in the East Hampton Star:

Negotiation
East Hampton
December 23, 2019

To the Editor:

Initially, Citizens for the Preservation of Wainscott claimed that it supported the South Fork Wind Farm but did not want the cable buried under Beach Lane. Interesting, Wainscott made no objection earlier in the year to East Hampton Town and Suffolk County burying nine miles of water pipe in Wainscott roadways (including Beach Lane) when the water quality of Wainscott’s aquifer was called into question.

Next, C.P.W. argued that the cable should come ashore at Hither Hills. The plan was to bury it under Montauk Highway from Hither Hills through Amagansett and East Hampton Village and then up Route 114 to the Cove Hollow Road substation. This would be very disruptive to homes, businesses, and traffic along this 11-mile route. This would take two off-seasons to complete. When asked why this was preferable, Citizens for the Preservation of Wainscott had no answer. F.Y.I., Beach Lane has six year-round residences.

Now, C.P.W. is opposed to the wind farm because the price negotiated with LIPA is too high. The agreement between Deepwater/Orsted and LIPA (which was approved by the New York State Public Service Commission) was the result of a public bid, which Deepwater/Orsted won because it provided electricity at the lowest cost. Now, four-plus years later, new wind farm bids are coming in even lower. Such prices will benefit South Fork residents since PSEG prices are based on a mix of all the prices it pays for the electricity it delivers. Lower prices for power from the newer wind farms will lower PSEG costs, and thus bills to consumers will go down.

Recently, C.P.W. claimed, without any supporting details, that within five years there would be more efficient and affordable ways to solve the power needs on the East End. Ninety-nine percent of scientists agree climate change is a current crisis. We need immediate action to address South Fork power needs, air pollution, health risks, sea level rise, as well as the existential crisis of climate change.

Finally, C.P.W. complains that Orsted is breaking its promise to explore the Hither Hills route in the Public Service Commission settlement negotiations, which are ongoing. Significant time was spent on the Hither Hills route during those negotiations, and on Jan. 8, at the request of C.P.W., an additional settlement negotiation will be held to allow C.P.W. to present its alternative route.

Orsted has gone out of its way to cooperate with C.P.W. The only deception has been on the part of C.P.W., which has little credibility. Clearly, C.P.W. is just a small, moneyed Nimby group who wants electricity for Wainscott without any involvement or inconvenience on their part.

It’s time for C.P.W. to get with the program and support the wind farm, which will provide electricity to 70,000 South Fork homes, including the 700 or so in Wainscott.

JERRY MULLIGAN

Take-aways from the new LIPA Fact Sheet

For what it’s worth, here are my main take-aways from the new LIPA Fact Sheet (attached below with highlights added) on the South Fork Wind Farm:

1.       South Fork Wind Farm was the least cost solution to meet increasing electric demand on the South Fork and New York’s renewable energy mandates.

2.       LIPA’s share of New York State’s 9,000 MW offshore wind target is over 1,000 MW and SF Wind Farm is the first of many projects to meet the Long Island goal.

3.       The South Fork RFP Portfolio (Wind+Storage+Demand Response) will cost the average residential customer on LI between $1.39 and $1.57 per month.

4.       The price LIPA pays for the 90 MW SFWF starts at 16 c/kWh; the price for the additional 40 MW (contracted in Nov. ’18) starts at 8.6 c/kWh (this additional energy was the lowest cost renewable energy ever on LI at the time). The combined cost for the 130 MW would be about 13.7c/kWh in the first year. Prices escalate at an average 2% per year for 20 years. 

5.       Levelized Cost of Energy (LCOE) over 20 years for the combined 130 MW SFWF is 14.1¢/kwh (in 2018 dollars, using a 6.5% discount rate). Cost of other planned projects in the region are projected to be significantly lower but an ‘apple-to-apple’ comparison is difficult because these projects are much larger and benefit from economies of scale. They were also selected later and thus benefitted from lower industry price levels. 

6.       Prices for offshore wind power have declined rapidly in Europe due to increased investment and improving technology and we are now seeing price declines in the emerging U.S. offshore wind industry.

7.       LIPA’s future offshore wind purchases will total over 800 MW, and will cost less as a result of expected price decreases. LIPA will also buy an estimated 90 MW of offshore wind from the recently announced 1,700 MW of New York State projects (by NYSERDA).

8.       As a result of procuring offshore wind power spread out over many years (a decade or so) as prices decline, LIPA’s overall offshore wind portfolio cost will be minimized.

9.       When comparing costs of renewable energy to conventional sources we also need to account for costs which are typically not accounted for such as the cost of air pollution, climate, unknown fuel price risk, etc.

The bottom line, as I see it, is that all this demonstrates that the South Fork Wind Farm not only provides us with local, renewable and reliable power but does so at an affordable price. And over time we will get more and more offshore wind power at even lower prices. This will result in a very affordable average bill impact and could even provide significant savings over fossil fueled power if natural gas prices turn out to be higher than currently forecast.

I’m attaching a marked-up version of the LIPA Fact Sheet where I highlighted sections discussing some of the above points in context.

Best, Gordian Raacke, Executive Director

Renewable Energy Long Island

facebook.com/RenewableEnergyLongIsland

twitter.com/LIGreenGuide

page 1

page 2
page 2
page 3
page 4